Contract vehicles DWG NO. HS-2026-EXEC · SHT A-106

Data Center Contract Vehicles

Five vehicles and one procurement overlay, with the guaranteed maximum price at the center — how it is set, what it covers, where it ends, and what happens when an owner reads it as a cap on scope instead of a price for a defined scope.

What this is: a working reference for owners and owner's representatives. It describes the mechanisms as they actually run on a mission-critical program and says where each one fails. It is not an advertisement, it is not a recommendation for your project, and there are no case studies in it. Where a percentage or a lead time appears, it is industry context rather than measured data from a specific program.

60–70%
CMAR with a GMP — share of North American hyperscale and colocation campuses · context
52–104WK
OEM lead times on switchgear, generators and UPS · context
90%+
Builds running an OFCI overlay to get around those lead times · context
6ROWS
Vehicles and overlays compared in the matrix — cost-plus included
01 / Guaranteed maximum price

What a GMP actually is

A-106.1

A guaranteed maximum price is a price, not a budget with a lid on it. It is a fixed figure the contractor agrees to deliver a defined scope for, set at a stated point in design, administered open-book, and carrying a contingency the contractor manages plus a written formula for what happens to money that does not get spent. Everything that decides whether the number holds is in those qualifications. Almost none of it is in the number itself.

How the figure gets set

The construction manager is engaged in preconstruction and works to the owner's budget while the design advances. When the documents are far enough along to price, the budget is converted into a GMP. That figure is built from five lines: trade packages already bought, trade packages not yet bought and carried at an allowance, the contractor's general conditions, the contractor's fee, and contingency. Those five lines have very different certainty, and the GMP is only as firm as the weakest of them.

The date the GMP is signed therefore matters as much as the number in it. On a CMAR job the usual practice is to set the GMP once 80%+ of trade packages are bought out, because bought scope is priced scope. On a progressive design-build job the GMP typically lands around 60% design, early enough that the design can still be adjusted to reach it. Both of those are judgments about maturity, not schedules.

Set the GMP too early and the allowances are guesses wearing a contract. Set it too late and the design is frozen, so the only lever left is scope. The question worth asking at signature is not "is this a good price" but "how much of this have you actually bought, and what are you assuming about the rest".

Contingency, and what happens to savings

There are two contingencies on a well-run job, and they are not interchangeable. The contractor's contingency sits inside the GMP. It belongs to the contractor, is drawn at the contractor's discretion, and absorbs buyout variance and gaps in the scope the contractor owns. The owner's contingency sits outside the GMP and pays for owner decisions: added scope, betterments, an owner-caused delay, a change in the power strategy. A GMP that shows one line called "contingency", with no statement of who draws it and no monthly report of how much has been drawn, is a number nobody is managing.

Buyout is where the money actually moves. Each package is bought against the allowance carried in the GMP. If it comes in under the allowance, there is a saving. If it comes in over, the GMP absorbs it up to the available contingency. What happens to the saving is a contract term, and it varies: returned to the owner in full, split on an agreed formula, or — in the weaker contracts — left with the contractor. Three things are worth insisting on before award: the formula, the timing (at buyout, and again at closeout), and reporting that shows allowance, buyout and variance per package rather than one reconciled line produced at the end.

One more distinction that gets lost: an allowance is not a contingency. An allowance is a placeholder for scope that is known and not yet priced. Contingency is money for what is not known. A GMP padded with allowances and presented as firm is a GMP with an unpriced half.

What sits outside the GMP

The exclusions and clarifications are the most important pages of the document, and they are usually read last. A GMP will normally exclude: the owner's contingency; the design contract and the architect-engineer's fees; owner-furnished equipment, including long-lead OFCI gear unless it is written into the scope of work; utility company charges and utility-side work; permits, connection charges and impact fees; scope added after the GMP date; and escalation, unless the contract carries it as a discrete clause rather than inside a fixed price.

LineIn the GMP?Who controls it
Bought-out trade packagesYesCM, under the GMP
Unbought packagesYes, at allowanceCM — the allowance is where the risk sits
General conditions and contractor feeYesCM
Contractor's contingencyYesCM, drawn and reported to the owner
Owner's contingencyNoOwner
Design fees and the A/E contractNo — separate contractOwner
Owner-furnished and OFCI equipmentOnly if written into scopeOwner
Utility charges and utility-side workNoOwner, on the utility's schedule
Permits, impact and connection feesNoOwner
Scope added after the GMP dateNo — change orderOwner decision
EscalationOnly if the contract says soNegotiated, in writing

The failure mode: a cap on scope instead of a price for scope

The failure is rarely a contractor taking advantage. It is an owner reading "guaranteed maximum price" as "the building, capped" — and then, when the number comes under pressure, doing the only thing the contract makes easy: removing scope. Cooling redundancy, controls scope, commissioning, spare capacity and maintenance provisions come out to protect the number. The saving arrives once, in a buyout. The cost arrives every month the building runs.

A GMP is a price for a defined scope. If the scope is not defined, the guarantee is not a price — it is a cap on an argument. Two conditions have to hold for the number to mean anything: the scope attached to it is defined in the documents, and most of the money in it has actually been bought.

CMAR, CM-at-risk and cost-plus are not the same thing

The three terms get used as though they described one contract. They describe three, and only one of them transfers the buyout to somebody else.

CM agency. The construction manager is the owner's agent. It holds no trade contracts, carries no price risk, and there is no GMP at all. It advises, coordinates and administers; the owner holds the trade contracts and keeps every dollar of cost risk. If someone says "CM at risk" and then describes an agent with no price, that is CM agency under the wrong label.

CM at risk. The same firm continues from preconstruction into construction, holds the trade contracts, and delivers a GMP. Its preconstruction advice and its construction price come from the same party, which is the structural reason an owner on a CMAR job needs an independent review of the GMP rather than a review by the party that wrote it.

Cost-plus. Cost plus a fixed fee, or time and materials: reimbursable cost with a fee, no cap, no buyout mechanism and no price. It is the right contract where scope genuinely cannot be defined — emergency capacity, disaster recovery, an unscoped first cluster on a live site — and the wrong one on a program that had a year of design available.

VehicleHolds the trade contractsCarries buyout and design-gap risk
CM agencyOwnerOwner
CM at risk (GMP)CMCM, up to the GMP and its contingency
Progressive design-build (GMP)Design-builderDesign-builder, up to the GMP
Cost plus fee / time and materialsOwner or CMOwner, with no cap
IPD (target cost)The parties, jointlyShared profit pool first, then the parties
02 / Delivery vehicles

The five, and what each one holds

A-106.2

Each entry below is the mechanism, not the sales description. Read them against the matrix in section 03.

CMAR with a guaranteed maximum price

Dominant on hyperscale · owner risk moderate · fast, phased · the owner keeps the A/E

  • Two phases, one contract. Preconstruction first — constructability, VDC/BIM coordination, schedule modeling, budgeting, package strategy. Then construction under the GMP. The preconstruction phase is where the GMP is earned or lost.
  • The owner holds the design contract. That is the point of CMAR, not a detail. Direct control of specifications and of the white space topology stays with the owner, which is what distinguishes it from design-build.
  • Early packages. Civil, substation and foundation scopes can be bought and started before the drawings are 100% issued for construction. On a data center, that is where the schedule is actually won.
  • Open book. Cost is audited against actual labor, material and subcontractor buyout. Unused contingency and buyout savings are returned to the owner under whatever formula the contract carries — check which.

Design-build, and progressive design-build

Rapid deployment · owner risk low to moderate · fastest route to a priced scope

  • One contract for design and construction. A design error and a field error come back to the same party, which removes the interface where most schedule and most claims are generated.
  • Progressive design-build. The team is selected on qualifications and preconstruction fee, then designs with the owner until a transparent GMP is established at around 60% design. It is the version of design-build that keeps the owner in the design instead of handing over a fixed program.
  • Less design latency. Equipment availability and constructability feedback arrive while the design can still change, rather than after it has been issued.
  • The trade. The owner gives up granular equipment selection unless the Owner's Project Requirements nail it — basis of design, redundancy scheme, sequence of operation, controls architecture. If it is not in the OPR, it belongs to the design-builder.

Integrated project delivery, with target value design

Lean collaboration · shared risk pool · highest velocity, highest governance load

  • One multi-party agreement. Owner, lead designer, general contractor and the tier-one critical trades — electrical, mechanical, controls — sign the same contract.
  • Pain share and gain share. Team profit is tied to shared outcomes: target cost, PUE, commissioning milestones. An overrun hits the shared profit pool before it reaches base cost, which changes the conversation in the room.
  • Target value design. Design is engineered to meet a cost target instead of being designed first and estimated afterwards. The consequence is that cost conversations happen in week three rather than month nine.
  • Waiver of claims. The parties waive claims against each other except for gross negligence. That is the mechanism, and it is only worth anything if the owner has the bench to run the model.

Design-bid-build, lump sum

Traditional · owner risk high on design and delay · slowest sequence

  • Strictly linear. Design reaches 100% construction documents, then it is bid, then the low bidder builds. No overlap, no early packages.
  • Change order exposure sits with the owner. A design discrepancy, an omission or a differing site condition becomes a claim. Under the Spearin doctrine the owner warrants the adequacy of the design it furnished.
  • No contractor preconstruction input. No constructability review, no supply-chain pre-ordering, no clash resolution while the design is still flexible. On a data center that is usually fatal to the schedule, which is why this vehicle survives mainly where statute requires it.

OFCI procurement overlay

Critical path overlay · supply-chain risk owner-held · installation risk contractor-held

  • The owner buys the long-lead equipment directly. Medium-voltage transformers, switchgear, generators, UPS, chillers, CDUs — under master service agreements with the OEMs, not through the contractor.
  • Lead time comes off the critical path. Direct contracting removes contractor markup and, more importantly, lets procurement start 12–24 months before groundbreak so factory slots get locked instead of queued.
  • The risk does not disappear, it moves. Delivery, bill of lading sign-off, staging and storage, rigging, mechanical and electrical tie-in, factory witness testing, warranty start dates, damage before turnover. Each of those needs a written demarcation between owner, OEM and contractor. An OFCI program without that document is an argument with a purchase order attached.
  • It is an overlay, not a vehicle. OFCI layers onto whichever prime contract you choose. That is why it appears in the matrix as a row and not as an option.
03 / Comparison

Comparative matrix

A-106.3

Read across a row, not down a column. The vehicle that wins on cost certainty usually gives something up on speed, and the one that wins on speed usually gives something up on control.

Delivery vehicle Cost certainty Speed to market Design control Change order risk Preconstruction input Where it fits on a mission-critical program
CMAR / GMP High, at the GMP Fast, phased Complete — owner holds the A/E Moderate Extensive Campus builds, wholesale colocation, phased fit-outs on a live site
Design-build (progressive) High Fastest Owner's specs and OPR Low Continuous Standardized pods, modular edge, turnkey substations
Integrated delivery (IPD) Target value Very fast Collaborative Negligible, by waiver Deep integration Mega-hyperscale, dense liquid-cooling retrofits, live cutovers
Design-bid-build (DBB) Low — claims exposure Slowest Complete High None Public and agency facilities, statutory low-bid mandates
Cost plus fixed fee (CPFF) Very low Immediate Complete Not applicable — reimbursable Real time Emergency deployment, early civil and enabling work, disaster recovery
OFCI hybrid overlay OEM pricing locked Critical path buffer Component level, 100% Schedule interface Factory witness and VDC Switchgear, generators, chillers, transformers — anything long-lead
04 / Selection

Four questions that decide it

A-106.4
01

Schedule or design primacy

If the date is the constraint and the design is modular or repeated, progressive design-build. If control of the custom mechanical and electrical topology is the constraint, CMAR with the A/E contract held by the owner. Pick one as primary; the other becomes a trade you manage.

02

Decouple procurement from the critical path

Whatever the prime vehicle, put transformers, switchgear, generators and UPS on an OFCI program. Lead times of 52–104 weeks do not fit inside a construction schedule that is trying to be shorter than they are, and no delivery method fixes a missing switchgear slot.

03

Owner organizational capacity

IPD needs an owner team that can run target value design, co-location and joint audits. Without that team, IPD becomes a conventional job with a shared-loss clause and more meetings. Buy the model you can actually govern.

04

Market volatility and buyout timing

In a volatile labor or equipment market, a GMP set before buyout is a guess presented as a guarantee. Prefer the GMP with shared savings taken after 80%+ of trade packages are bought out, and keep the buyout variance visible package by package.

Contact

Start with the program

A-106.6

Send the project, the phase, and the contract decision you are trying to get right. If the answer is that your current vehicle is fine, that is what you will hear.

Send a Message
Open the contact form
Résumé
Request a copy
Back to top